The financial cooperation programme consists of the following components (results) which are in close synergy with the technical cooperation programmes and will be implemented in different phases: Phase 1 (covered by this contract) - Campaigns of large flow rates drilling in the towns and their surroundings of the four programme regions (selected towns: Bama, Banfora, Bérégadougou, Dandé, Diébougou, Houndé, Mangodara, Niangoloko, Orodara, Pa, Péni, Sideradougou, Sindou, Solenzo, Soubakaniédougou, Toussiana);
- Expansion of the water treatment plant capacity of Banfora from currently 240 m³/h to 500 m³/h;
- Construction of water main from Banfora to Panga and from Panga to Niangoloko in the south and to Soubakaniédougou in the north, as well as 65 water standpipes for water provision to the villages along the water line;
- Rehabilitation and expansion of the water treatment systems of Banfora and Niangoloko.
Further phases (depending on availability of funding) in the following order of priority - Energy saving measures by using hydraulic power for the water treatment system in Banfora and through solar energy production for the existing boreholes;
- Expansion of sewage network of Bobo Dioulasso and commissioning of 450 additional connections to the system (limited to studies);
- Support to ONEA in elaborating preliminary and detailed studies, preparing tender documents and in construction supervision;
- Carrying out a hygiene awareness programme in the 16 programme towns;
|